Street Improvement on N. Second, N. Third, and Parkway Ave
Project Timeline
Project Area Map
Estimated Annual Property Tax Impact
Reports http://www.bolton-menk.com/clients/eaglelake/index.htm
| Name | Extension |
Preliminary Engineering Report - Copy available at City Office at cost of printing
2nd and 3rd Street and Parkway Avenue Improvements
The street and utilities along Second and Third Street and the watermain along Parkway Avenue were originally constructed over 60-years ago. Currently, the existing streets and utilities along Second and Third Street and the watermain along Parkway Avenue are deteriorated and in need of repair. If the infrastructure is not replaced, maintenance costs will continue to rise as further deterioration occurs, and ultimately the street and utilities will fail.
The proposed improvements include the replacement of the existing municipal utilities, bituminous surface, and curb and gutter, and the addition of concrete sidewalk. The reconstruction would also include the replacement and addition of storm sewer to improve drainage along the street.
The estimated cost of the proposed improvements is $1,196,000.